Six-Month Basslink Investigation Comes Up Empty-Handed

3/9/2017

1 Comment

 
A six-month investigation into the fault that downed the Basslink subsea electricity and data cable connecting Tasmania to mainland Australia late last year has been unable to identify the cause of the cable cut.

Figure 1 - Basslink Network Map
Picture
Source: Basslink

The Basslink cable spent six months offline following the December 2015 fault, causing big problems for Tasmanian internet providers and end users.

Basslink has been working on a full fault diagnosis since the cable began operating again in June.
However, despite subsea cable experts Cable Consulting International spending more than six months undertaking forensic examination, lab analysis, and materials testing as part of its investigation into the issue, Basslink today said it still had no idea how the cut had occurred.

The official finding of CCI's report was "cause unknown".

Basslink said CCI had been able to determine that the fault had occurred within the cable - not at a joint, for example - and that there had been no pre-existing mechanical damage. It also said the operating conditions around the time of the cable failure had been no different to normal.

"The point of initiation within the fault path and the direction of propagation of the electrical failure could not be determined due to the severity of the fault damage," Basslink said.

Basslink chief executive Malcolm Eccles said it was "not uncommon" that the cause remained unknown, based on other similar outages.

“The silver lining in this whole exercise is that CCI found the other section of the cable it sampled to be in sound condition. This gives us confidence in the long-term outlook of the asset," he said in a statement.

Eccles said Basslink had handed over the report to Hydro Tasmania and the Tasmanian government.
He said the report supported Basslink's long-running argument that the fault was a "force majeure event".

"Given this, we would like Hydro Tasmania to recommence meeting its contractual obligations to Basslink immediately," he said. Hydro Tasmania had stopped paying its fees to the cable operator following the downtime because it disagreed with the cause of the fault.

The report marks the end of the investigation into the fault for Basslink; it said it would not undertake any further testing."

Source : www.itnews.com.au

ANALYSIS: The lack of a conclusion in this investigation will raise eyebrows among the submarine fiber optic community but the stakes are high because Basslink is a hybrid power and telecom cable.

Figure 2 - Photo of Basslink Cable Break​
Picture
Source: http://www.abc.net.au

An investigation of this nature into a fiber optic break would, at the very least, be able to say whether the damage was caused by external aggression or some internal fault. No such information has been provided in this case and the reason is clear: power company, Hydro Tasmania, Basslink's only customer on the electricity transmission side of the business, has stopped paying and is rejecting Basslink's claim of force majeure. It is therefore in the interests of Basslink to draw an inconclusive line under this event to avoid undermining its claim. Hydro Tasmania has indicated that the dispute will end up in court though. This would suggest that further independent investigations of the cause of this cable break may be in the offing.​
1 Comment
nexa electrical supplies link
2/21/2020 12:53:58 am

thanks for providing useful information on Six-Month Basslink Investigation Comes Up Empty-Handed

Reply



Leave a Reply.

    Julian Rawle, Author

    Thought leadership articles and commentary on developments related to the subsea fibre optic cable industry can be found here.

    MarineTraffic AIS Ship Data & Live Map Positions

    INDUSTRY PULSE: Retelit Trades AAE-1 Capacity for Asian Services… SEAIOCMA Extends Cable Maintenance Contract with Global Marine… Djibouti Africa Regional Express (DARE) Submarine Cable System Contract in Force... Tui-Samoa Submarine Cable System Final Splice Completed... Xtera Initiates Legal Action against Nokia and NEC for Alleged Patent Infringement... Basslink Subsea Cable Outage Caused By Exceeding Design Limit: Experts... ANTONIO MEUCCI arrived at port CATANIA... ASEAN EXPLORER departed from port SEMBAWANG... ASEAN RESTORER departed from port SEMBAWANG... BOLD MAVERICK departed from port SINGAPORE... CABLE INNOVATOR departed from port VICTORIA... CABLE RETRIEVER departed from port SUBIC BAY ... DECISIVE arrived at port LAS PALMAS... DEPENDABLE departed from port CAPE TOWN... DURABLE arrived at port JINGJIANG... CS ETISALAT departed from port HAMRIYA... FJORDKABEL arrived at port HARSTAD... FU AN arrived at port MINHANG... FU HAI departed from port KITAKYUSHU... GLOBAL SENTINEL departed from port HONOLULU, HI... ILE DAIX departed from port PALMONES... ILE DE BATZ arrived at port CALAIS... ILE DE BREHAT departed from port RIO DE JANEIRO... ILE DE RE departed from port SUVA... ILE DE SEIN departed from port NORFOLK, VA... IT INTREPID departed from port CAPE CANAVERAL, FL... KDDI OCEAN LINK departed from port YOKOHAMA... KDDI PACIFIC LINK arrived at port MOJI... KIZUNA arrived at port NAHA... LEON THEVENIN departed from port CAPE TOWN... CS LIMIN VENTURE departed from port BATU AMPAR... LODBROG departed from port KEELUNG... MAERSK RESPONDER departed from port PASIR GUDANG... MARAM departed from port FREE PORT... NIWA arrived at port SALALAH... NORDKABEL arrived at port BOKN... PACIFIC GUARDIAN arrived at port WILLEMSTAD... PETER FABER arrived at port MINDELO... PIERRE DE FERMAT arrived at port HOEK VAN HOLLAND... RAYMOND CROZE departed from port CATANIA... CS RECORDER arrived at port BLYTH... RELIANCE arrived at port NOUMEA... RENE DESCARTES departed from port LUANDA... RESOLUTE arrived at port KEELUNG... RESPONDER departed from port AUCKLAND... SEGERO departed from port SHANTOU... SOVEREIGN arrived at port PORTLAND, UK... SUBARU departed from port NAGASAKI... TELIRI departed from port CAPE TOWN... TENEO arrived at port WILLEMSTAD... UMM AL ANBER departed from port HAMRIYA... VEGA departed from port BATANGAS BAY... WAVE SENTINEL arrived at port WILLEMSTAD...
    Picture
    Julian Rawle participated in the Submarine Networks World Conference 8-10 September 2015 in Singapore

    Archives

    February 2018
    December 2017
    November 2017
    September 2017
    August 2017
    July 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    January 2016
    December 2015
    November 2015

    Categories

    All

    RSS Feed

Julian Rawle Consulting
38 Hickory Lane
North Reading, Massachusetts
01864    USA

Direct:  +1 617.417.6321
Fax:  +1 978.207.1035
Email:  j.rawle@consultingjulian.com

Tweets by @JulianRawle
BACK TO TOP

© Julian Rawle Consulting  |  All Rights Reserved  |  Website Created by LislDesign.com

JULIAN RAWLE CONSULTING